Leveling plumbing bids

What plumbing bids usually cover, what they leave out or qualify, and the alternates and unit prices worth lining up across bidders.

Plumbing bids split cleanly in theory and messily in practice. The usual boundaries (five feet outside the building, fixtures by owner or by contractor, roof drains with plumbing or roofing) are where bids differ most.

Underground work under the slab is the other place to look closely: sawcutting, excavation and backfill are often excluded or carried as unit prices.

Typical scope items

What a complete plumbing bid usually prices, and what to check in each:

Scope itemWhat to check
Domestic waterPiping from the point of connection, with valves, backflow prevention and insulation if specified.
Sanitary waste and ventUnderground and above ground. Check which portions each bid includes.
Storm drainageRoof drains, overflow drains and leaders. Roofing flashes the drains plumbing sets.
Fixtures and trimFurnished and installed, installed only (owner furnished), or excluded.
Water heaters and equipmentNote the equipment carried against the basis of design.
Natural gas pipingSometimes with mechanical. Make sure it is carried once.
Testing, flushing and disinfectionUsually included; confirm it is stated.

Common exclusions and qualifications

Not every exclusion is a problem. Some are fair because the work belongs elsewhere. The ones below are where plumbing bids most often differ, so read them against the other bidders.

Often excludedWhy it matters
Site utilities beyond a set distance from the buildingCommonly excluded beyond five feet. The sitework bid needs to pick it up.
Tap, impact and meter feesOften excluded. Carry them as an allowance if no bid includes them.
Sawcutting, excavation and backfillUnder-slab work in an existing building is a common exclusion.
Rock excavation and dewateringUsually excluded or carried as a unit price.
Fixtures furnished by the ownerFine if that is the plan; check the bid installs them.
Fire protectionSprinklers are normally a separate trade package.
Kitchen and process equipment connectionsFrequently excluded or limited to stub-outs.

Alternates to watch

  • Fixture upgrades or substitutions
  • Tankless or alternate water heating equipment
  • Additional fixtures or restrooms

Line alternates up by the numbers on your bid form, keep add and deduct straight, and treat an unpriced alternate as a question, never as zero.

Unit prices and allowances to compare

  • Sanitary or water line, per linear foot
  • Rock excavation, per cubic yard
  • Sawcut and patch slab, per linear foot
  • Utility fee allowance

Compare rates only where the units match, and note any quantity already included in the base bid.

Where plumbing meets other trades

Gaps and double counts happen at the edges. Read these packages together:

  • Sitework (utilities outside the building)
  • Roofing (roof drains and overflows)
  • Mechanical (gas piping, condensate)
  • Concrete (sawcutting and slab patching)

How Bidtab lays out plumbing bids

Upload each bidder's PDF to one project for the package. Bidtab reads every bid and shows, side by side and in the order you uploaded them:

  • each base bid, as stated;
  • alternates aligned by number and description, with add or deduct for each bidder;
  • a scope row for each item the bids address, with every bidder marked Included, Excluded, Qualified or Not stated;
  • allowances and unit prices, with their units;
  • each bidder's exclusions and qualifications as written;
  • open questions where a bid is silent on an item other bidders addressed, where a figure isn't printed on the page it came from, or where line items don't add up to the total.

Every figure shows the page and words it came from, and the whole comparison exports to an Excel workbook. Bidtab doesn't rank bidders or price excluded scope; those calls stay with you. See the sample project (a roofing package) for the layout.